Construction Change Order Log Template and Weekly Review

Construction Change Order Log Template and Weekly Review

Construction Change Order Log Template and Weekly Review

An approved change can still miss the next invoice. The project manager has the approval, the site team has the revised drawing, and the office is billing from last month’s list. A construction change order log gives the team one place to check what needs pricing, what is waiting on a decision, and what is approved but still unbilled.

An approved change can still miss the next invoice. The project manager has the approval, the site team has the revised drawing, and the office is billing from last month’s list. A construction change order log gives the team one place to check what needs pricing, what is waiting on a decision, and what is approved but still unbilled.

Download the Excel template

Free .xlsx workbook with a blank log and worked examples.

Use the template below for one job, then bring its open items to your weekly project review. Give every item an owner, a due date, and a next action that someone can complete.

Change order log versus change order form

Change order log versus change order form

A change order form describes one proposed change to the construction contract. It usually records the requested work, the price and schedule impact, and the approval required by your project. A construction change order log is the running list of all those changes. Use the form to document a decision and the log to see which decisions and invoices still need attention.

Open the log when the original scope is agreed. Add a row when a request or site condition could change the work, even if you are still waiting on details. Save the supporting documents under the same change order number so a new project manager can trace the decision without searching through email.

What to put in your change order log

What to put in your change order log

Use one row per potential change and keep its ID as it moves through pricing, approval, and billing. These three entries show a Friday snapshot from a fictional residential addition.

CO-07 · RFI-14

Approved, unbilled

Move the duct around a revised beam. Allow one extra day before the ceiling closes.

$2,600 estimated direct cost · $3,450 approved · $0 billed

Office lead adds it to Tuesday’s progress invoice.

CO-08 · Site photo 23

Needs pricing

Repair damaged subfloor and check whether the flooring start date will move.

Direct cost and client price pending

Estimator confirms labour and material costs by Monday.

CO-09 · Client email

Awaiting approval

Add an exterior outlet. Confirm the change before the wall closes.

$240 estimated direct cost · $360 proposed

Project manager follows up on the submitted price by Monday.

Use the source column to link to the RFI response, drawing revision, photo, or client request. When a change is approved, add a reference to the approved document and record the approval date. When it’s billed, add the invoice number. Keep the original scope and the approved change easy to find so the next reviewer can see how the agreement evolved.

Keep direct cost and client price in separate columns. Direct cost is what you expect the added work to cost your company. Client price is the amount you propose or agree to charge. To calculate the unbilled balance, subtract the amount already invoiced from the approved price on the same tax basis. Keep pending prices outside that total and update the balance after each invoice if a change is billed in stages.

How one change moves from RFI to invoice

How one change moves from RFI to invoice

On the fictional addition, the superintendent finds that a revised beam crosses the planned duct route. The project manager opens RFI-14, attaches a sketch, and asks the designer to confirm an alternative route. The reply provides the scope needed to price the change. The project manager records it under CO-07 and checks when the ceiling crew can return.

The estimator uses the mechanical trade’s quote and the crew’s labour estimate to put direct cost at $2,600. The project manager submits a client price of $3,450 with the extra day stated. That leaves $850 in estimated gross profit before overhead. When the client approves, the project manager saves the approval, checks the revised contract amount against the approved change, and reviews where the additional cost belongs in the project budget.

At Friday’s review, the full $3,450 is still unbilled. The office lead takes ownership and adds it to Tuesday’s progress invoice. Once the invoice is issued, the office lead records the invoice reference and updates the billed amount to $3,450. The change drops out of the unbilled queue, and the team can still trace it back to the designer’s response.

What to check in the weekly review

What to check in the weekly review

1. Needs pricing

Check which scope details or trade quotes are missing. Assign the next request to one person and agree on a due date.

2. Awaiting approval

Look at work coming up on the schedule. Confirm who owns the follow-up and flag any crew or material decisions that depend on the response.

3. Approved but unbilled

Compare approved changes with issued invoices. Assign the remaining amount to a specific billing cycle and confirm who will reconcile it.

End the review by reading back the next actions and dates. If an item carries over to the following week, its owner should be able to explain what’s holding it up and what will move it forward.

How to log partial invoices and credits

How to log partial invoices and credits

If you bill $1,200 of the $3,450 approved for CO-07 on one progress invoice, the remaining balance is $2,250. Keep the same change order number, record the invoice reference, and update the billed amount as each invoice goes out. The log should show the running total; the invoices provide the itemized record.

For a credit, use the same sign for the approved amount and the amount issued. An approved $400 credit appears as −$400. If you issue a $150 credit, record −$150 and keep the remaining −$250 visible as a credit still due. Keep pending and declined changes in the log for reference and leave them out of the approved billing balance.

Review change orders in Konstructo

Review change orders in Konstructo

In Konstructo, you can review RFIs in Project Coordination and open the same job’s change orders, budget, and client invoices during a financial review.

Explore cost management

See how RFIs are organized

Bring one change order to a walkthrough and follow it from the project record into financial review.